TR
|
Description
|
Responsible
|
Contract Date
|
Current Date
|
|
TR1 |
Comparative study
of spatial data aggregation techniques |
CTU |
December 1999 |
Finished |
|
TR2 |
Metadata language
specification |
VUT |
May 1999 |
Finished
|
|
TR3 |
Analysis of OLAP
modifications |
VUT |
December 1999 |
Finished |
|
TR4 |
Integration module
specification |
CTU |
December 1999 |
Finished |
|
TR5 |
Integration module
documentation |
CTU |
July 2001 |
Finished |
|
TR6 |
Data security
concepts |
UE |
December 1999 |
Finished |
|
TR7 |
Security layer
specification |
UE |
September 2000 |
Finished |
|
TR8 |
Application A1
specification |
VEGA |
March 1999 |
Finished
|
|
TR9 |
Application A1
documentation |
CERT |
May 2001 |
Finished |
|
TR10 |
Security evaluation
report |
UE |
January 2001 |
Finished |
|
TR11 |
Application A2
specification |
LUM |
March 1999 |
Finished
|
|
TR12 |
Application A2
documentation |
LUM |
May 2001 |
Finished |
|
TR13 |
Specification of
background spatial knowledge representation |
CTU |
July 2000 |
Finished |
|
TR14 |
Simulation module specification
and documentation |
VUT |
November 2000 |
Finished |
|
TR15 |
KDD package design |
TUK |
September 1999 |
Finished
|
|
TR16 |
KDD package
evaluation |
TUK |
August 2001 |
Finished |
|
TR17 |
Tutorial of Sumatra Embedding |
CTU |
Not required |
Finished |
|
TR18 |
Description of Integration Module Prototype |
CTU |
Not required |
Finished |
|
TR19 |
Prototype Applications |
CERTICON |
Not required |
Finished |
|
TR |
Description |
Responsible |
Contract Date |
Current Date
|
|
SP1 |
Prototype
of modified OLAP (ver 1) |
TUV |
September 2000 |
Finished |
|
SP2 |
Prototype
of integration module |
CTU |
September 2000 |
Finished |
|
SP3 |
Prototype
of modified OLAP (ver 2) |
TUV |
July 2001 |
Finished |
|
SP4 |
Prototype
of application A1 |
CERT |
October 2000 |
Finished |
|
SP5 |
Prototype
of application A2 |
LUM |
October 2000 |
Finished |
|
SP6 |
Prototype
of simulation module |
VEGA |
May 2001 |
Finished |
|
SP7 |
KDD
techniques package |
TUK |
January 2001 |
Finished |
Id
|
Description |
Responsible |
Contract Date |
Current Date
|
|
PR1 |
Progress
Report - 1st year |
CTU |
September 1999 |
Finished |
|
PR2 |
Progress
Report - 2nd year |
CTU |
September 2000 |
Finished |
|
PR3 |
Progress
Report - 3rd year |
CTU |
September 2001 |
Finished |
CTU - the
co-ordinator of WP7 - Management assembled both management reports and cost
statements.
Management
reports reporting the 6 months long periods were provided by each partner to
CTU within the month following the reported period. Contributions from
particular partners were processed by CTU into Project Management Report. After
approval by the Project Co-ordinator the Project Management Report was
delivered to the Programme Directorate not later than two months after reported
period.
The same
reporting period (6 months) and organisation were used for reporting the cost
statements.
Reviews were
organized regularly one month after the date of each milestone